Project Overseer: Paul Babalola
Duration: 3 Months (12 weeks)
Phase 1: Requirements Gathering
Duration: 2 weeks
Deliverables:
- Requirements document detailing functional and non-functional requirements.
- Business case review and validation.
Milestone: Finalized and approved requirements by stakeholders.
Task Breakdown:
- Functional Requirements Collection (5 days)
- Conduct meetings with stakeholders to gather system requirements.
- Define key system features (e.g., feedback collection forms, admin dashboard, report generation).
- Assigned to: Business Analyst ( Jane Doe)
- Non-Functional Requirements Definition (3 days)
- Establish performance metrics, security concerns, and user experience criteria.
- Assigned to: Business Analyst (Jane Doe)
- Approval of Requirements Document (2 days)
- Review and finalize the document.
- Conduct approval meeting with stakeholders.
- Assigned to: Project Manager (Paul Babalola)
Requirements Gathering
Phase 2: System Design
Duration: 3 Weeks
Deliverables:
- System architecture diagram (front-end & back-end).
- Database schema design.